Lake Erie Energy Development Corporation

Updated: 4:55 p.m., Friday, Sept. 18, 2020

The Ohio Power Siting Board (OPSB) has repealed a provision requiring a proposed wind farm in Lake Erie shut down its turbines overnight from March 1 to Nov. 1.

Board members unanimously approved a motion by Mary Mertz, director of the Ohio Department of Natural Resources, to remove the requirement at the OPSB meeting Thursday.

Erik Drost / Flickr

A $126 million plan to put six wind turbines in Lake Erie is one step closer to winning final approval. 

The wind farm would include six turbines located in Lake Erie about 10 miles from the shore.
WKSU

Developers planning a power-generating wind farm in Lake Erie are preparing to take their case to Columbus later this month.